Parks update: city outlines timelines for playground, Swim Center and Demuth Park projects
City staff told the Parks and Recreation Commission that construction on new playground equipment for Desert Highland Park could start in the next month, while the Swim Center awaits an expanded assessment.

Palm Springs staff updated the Parks and Recreation Commission on Monday on major park projects, including a Desert Highland Park playground that could begin construction as soon as next month.
City Project Manager John Brickley said all contracts for the playground replacement are executed, but the start date depends on permits. Final plans were submitted Nov. 9, and the city received a request Oct. 28 for additional structural calculations. The Building and Safety, Engineering and Planning departments are expediting reviews, and contractors are on standby.
Local reporting and journalism you can count on.
Subscribe to The Palm Springs Post
Demolition and site preparation would come first, followed by equipment and shade structure installation, rubberized surfacing, lighting and final inspections. Completion is anticipated in February or March 2027, depending on the start date.
Construction may continue through February, which is Black History Month. Brickley said he told the Desert Highland Gateway Estates Community Action Association that “there will be a fence up and it’ll be under construction.” Staff will keep coordinating with the group on Black History Month events and programming.
At the Palm Springs Swim Center, staff are expanding an assessment of the pool complex because the facility’s problems have grown since the city’s 2024 plan. Parks and Recreation Director Nick Gonzalez said staff have been patching a system that has seen more failures.
“That facility is over 50 years old,” Gonzalez said. “It hasn’t had significant work to it. The equipment reflects that.”
The Palm Springs Swim Center assessment will cover the entire pool complex and supporting elements outside the new building project. Gonzalez said staff want the expanded scope to be complete. “We want to make sure that nothing’s missed and that we’re upgrading all the systems accordingly,” he said.
A separate aquatic feasibility study will look at new or additional aquatic facilities across the city, Brickley said. Both scopes of work are in review with the Engineering, Planning and Building and Safety departments, and the city will issue requests for proposals once the scopes are final. Brickley said the consultants’ responses will provide timelines and preliminary cost estimates.
Brickley said the city can repair the existing heaters but cannot simply buy new ones because of new state laws and regulations. “We can’t just buy a new heater and plug it in,” Gonzalez said.
Construction documents are underway with Interactive Design Corp. for the Swim Center locker room and office renovation. Updates on a delivery timeline and initial cost estimates are pending. Brickley said he was meeting with the design team Tuesday to finalize elements and work toward a more confirmed schedule. He told commissioners the recent changes are minor and do not alter the structure or layout.
“Unfortunately, it’s a lot of work that’s happening behind the scenes that you’re not necessarily seeing movement on, but we’re actively working on this,” Gonzalez added.
One commissioner hoped that there could be more communication with swimmers about the status of the project. Gonzalez said they would look into putting up a sign with a QR code at the swim center to direct residents to a website with more information.
At Demuth Park, Brickley said all remaining parts of the improvements project are under active construction. The AYSO and community center parking lot is complete, and the small dog park opened last week. Large dog park grading, restroom finalization and the community center parking lot expansion are still under way.
Staff now target mid-January 2027 for completion. “Some of that got pushed out,” Brickley said, because Southern California Edison must de-energize a large portion of the park’s electrical switchgear, which requires a two-week lead time. Half of the parking lot, the large dog park and the new restrooms all must be connected afterward, he said. The work will not affect the community center.
The Ruth Hardy Park workout space is scheduled to go to the City Council on Dec. 9 for final approval. Brickley said the staff report is ready and a final pricing audit is under way. “I don’t anticipate any issues,” he said. Work is expected to begin in spring 2027.
Also at Ruth Hardy Park, staff are working with a grant writer to secure U.S. Tennis Association funding for a tennis court assessment and redevelopment design. The city is awaiting a response on the application and is planning community outreach, including a tennis town hall, now that the Demuth Park pickleball courts are complete.
Brickley said staff “really need to get out there and have another meeting with the tennis committee sometime in the new year.”
In other updates, Construction at Downtown Park is underway for the AIDS Memorial, with the concrete disc, benches and center post installed. Marble and mirror elements are in place, and terrazzo and inlay work continues. A dedication ceremony is scheduled for Dec. 1.
At Tahquitz Creek Golf Course, Brickley said improvements are “kind of in limbo” while staff coordinate with the Historic Site Preservation Board on patio expansion plans. Staff also are evaluating cooling system upgrades for the golf cart barn.
For the Victoria Park restroom:The new Victoria Park restroom is constructed, and will be operational Dec. 8, the old restroom will then be demolished and the site left as open space.